STUDIO NOIR · Buildout Specification
Phase 1 is a lean fit-out of a small leased space by one licensed general contractor. Not a full architect + MEP + acoustic team engagement (that’s Phase 2 flagship).
Design intent is preserved: STUDIO NOIR reads as luxury even at boutique scale. Materials chosen to honor the palette without breaking the $40K buildout budget.
Phase 1 buildout scope (~1,800 sqft)
Broken into 10 line items. Total $40,000. Cross-reference 05_FINANCE/00_STARTUP_BUDGET Bucket 3.
1. Sprung floor system + marley top layer ($8,000)
- Full studio floor coverage (~1,600 sqft)
- Sprung sub-floor with resilient rubber pads underneath
- Marley top layer in a warm neutral color that reads with the palette
- Suppliers: Harlequin Liberty or Rosco Cadence
- Installed by GC’s flooring sub
Why non-negotiable: Pole and dance safety. A concrete floor with poor absorption injures members and destroys the brand promise.
2. Mirror wall installation ($4,500)
- 36 to 48 linear feet, floor to ceiling
- Silvered glass, not acrylic
- Champagne Gold trim frame on the outside edge
- Installed by GC’s glass sub with wall bracing for weight
3. Six pole rigs installed ($6,000)
- Xpole or Lupit brand poles
- 45mm diameter (industry standard)
- Removable for dance-only class configurations
- Ceiling reinforcement (steel plate + engineered attachment) per structural engineer’s spec
- Installed by a CERTIFIED RIGGER (not general labor). Certification required by insurance carrier.
Why the rigger matters: Insurance liability requires certified installation. A DIY or unqualified install voids liability coverage and creates a lawsuit-magnet situation. This line item cannot be cut.
4. Sound system ($3,500)
- Amplifier: mid-tier commercial (Crown, QSC)
- 4 mounted speakers (2 near ceiling front, 2 rear)
- 1 subwoofer positioned along a wall
- Wall-mounted volume control at reception
- Optional: bluetooth + wired input at reception for instructor phone connection
- Tuned by Trill or an approved audio person, not the GC’s default
5. HVAC upgrade or supplemental cooling ($5,000 contingency)
- Assessment by licensed HVAC contractor BEFORE lease signing
- If base HVAC handles a hot pole class (12 people, cardio-level output): no upgrade needed. This budget line can pull.
- If marginal: add supplemental spot cooling unit (portable or ceiling-mounted mini split)
- If severely inadequate: this is a walk-from-the-deal signal
6. Restroom refresh ($4,000)
- 1 or 2 existing restrooms (Phase 1 relies on landlord’s existing plumbing)
- Fresh paint in the palette (Soft Cream walls, Warm Taupe accent)
- New luxury fixtures (Kohler, Toto, or equivalent, matte black or Champagne Gold finish)
- New full-length mirror in each
- Warm dimmable lighting fixture replacement
- No plumbing changes (that would blow the budget)
7. Reception + concierge desk millwork ($2,500)
- Custom oak desk (rift-sawn, oiled finish, no gloss)
- Champagne Gold hardware
- Built-in champagne cooler cutout (member cooler runs on standard 120V)
- Prosecco flute display shelf
- Signature scent diffuser cutout
8. Paint and interior finishes throughout ($2,500)
- All walls: two coats. Studio in Soft Cream. Reception + concierge in Warm Taupe.
- Ceilings: existing painted matte cream, or if exposed structure, painted Black Noir
- Trim throughout in Champagne Gold or matte black
- All labor + materials
9. Signage: exterior + interior ($2,000)
- Exterior sign at entrance: brushed oak with Champagne Gold foil-pressed STUDIO NOIR wordmark
- Small interior wayfinding plate: brass, engraved
- No neon. No vinyl.
10. Lighting fixtures + dimming controls ($2,000)
- Replace existing overhead fluorescents with warm dimmable LED fixtures
- Wall-mounted Lutron dimmer switches
- 2700K temperature throughout
- Accent lighting at reception (single pendant, Champagne Gold shade)
Total: $40,000.
Design intent (Phase 1 vs Phase 2)
Both phases share the same brand and material palette. Phase 1 executes the palette at lower unit cost and smaller scale.
Phase 1 uses: - Warm oak (reception desk, minimal accents) - Champagne Gold hardware - Soft Cream walls and Warm Taupe accents - Black Noir where structural (exposed ceiling, steel frames) - Sprung floor + marley (movement surface) - Cream linen soft goods (towels for members) - Cream stock paper printed materials (member folios)
Phase 1 does NOT use (all Phase 2): - Travertine floor (too expensive Phase 1) - Roman clay plaster walls (nice-to-have not need-to-have) - Espresso oak paneling (Phase 2 café) - Custom black steel mirror frames (Phase 1 uses standard Champagne Gold trim) - Espresso velvet (statement pieces at flagship) - Bespoke leather bench upholstery - Live plants (not in the palette, but tempting) - Reclaimed exposed brick features (only if the space already has them)
Materials palette applied (Phase 1)
| Surface | Material | Cost tier |
|---|---|---|
| Studio floor | Sprung floor + marley | Essential |
| Reception floor | Existing floor cleaned, or engineered oak plank if affordable | Essential |
| Walls (studio) | Soft Cream paint (Benjamin Moore or Sherwin-Williams equivalent) | Essential |
| Walls (reception) | Warm Taupe accent | Essential |
| Reception desk | Oak millwork, custom | Essential |
| Hardware | Champagne Gold (door pulls, mirror frames, signage) | Essential |
| Mirrors | Full-height silvered glass | Essential |
| Ceilings | Existing (painted) or exposed structure (Black Noir if industrial) | Essential |
| Restroom fixtures | Kohler or Toto, matte black or Champagne Gold | Essential |
| Lighting | Warm dimmable LED | Essential |
| Soft goods (member towels, robes) | Cream linen | Nice-to-have Phase 1, ~$500-1000 sourced separately |
No visible plastic anywhere member sees
Applies Phase 1. No plastic signage. No plastic laminate. No vinyl wayfinding. If a material would look cheap on inspection, it doesn’t go in.
Compliance and code Phase 1
- ADA compliant (accessible entry, accessible restroom, no unramped steps)
- Fire code + occupancy limits per local code (Raleigh, Cary, or Durham depending on final site — roughly 30-40 person max at this footprint)
- Sound levels compliant with local municipal ordinances
- Health department not required for Phase 1 (no food service)
- No ABC license required for Phase 1 (prosecco service under NC “special ABC permit” for members-only events; small pour at entry may qualify as complimentary hospitality — legal check with attorney)
Buildout timeline Phase 1
Target: 6 to 10 weeks from lease signing to soft open.
- Weeks 1-2: Permit applications, structural check confirmed on file, GC mobilization.
- Weeks 2-3: Demo any existing partition walls, restroom scope prep, floor prep.
- Weeks 3-5: Sprung floor + marley install, ceiling reinforcement for pole rigs, mirror wall install, restroom refresh.
- Weeks 5-7: Reception millwork install, paint, lighting fixture replacement, HVAC tune (if needed), signage install.
- Weeks 7-8: Poles installed by certified rigger, sound system installed and tuned, final punch list.
- Weeks 9-10: Booking software (Mariana Tek) configured, class schedule loaded, contract instructors onboarded, cleaning company retained, opening supplies stocked.
Soft open (invite-only, charter member cohort) by week 10.
Phase 2 buildout spec (preserved for reference, rewritten in 2028)
Phase 2 flagship (8,000 to 15,000 sqft) requires: - Full architect + interior design partner + AoR (Architect of Record) - MEP engineer - Structural engineer of record - Acoustic consultant (WSDG or Acentech for the broadcast dual-mode brief) - GC selected via preconstruction services engagement + GMP (Guaranteed Maximum Price) contract
Full Phase 2 spec includes: - 20 to 24 pole positions on independent rigging grid - Broadcast-ready main studio with retractable seating (150-200), motorized theatrical lighting truss, Dante audio network, streaming rack, control room - Recovery wing (sauna, cold plunge, steam, contrast) with dedicated MEP - Full commercial kitchen for café with Type I hood - Locker rooms (M / F / gender-neutral) - Members’ lounge and café - Retail micro-boutique - Loading dock for broadcast production access
Phase 2 hard construction cost estimate: $2.5M to $3.5M. Full build budget in 06_BUILDOUT_BUDGET Phase 2 section.
Phase 2 buildout timeline: 24 to 32 weeks after permit issuance.
Related docs
- Property targets: 04_REAL_ESTATE_BUILDOUT/00
- Broker roster: 04_REAL_ESTATE_BUILDOUT/02
- Architect + GC (Phase 2): 04_REAL_ESTATE_BUILDOUT/04
- MEP + structural + acoustic (Phase 2): 04_REAL_ESTATE_BUILDOUT/05
- Buildout budget: 04_REAL_ESTATE_BUILDOUT/06
- Startup budget: 05_FINANCE/00