STUDIO NOIR · Architect and GC Shortlist
Phase 1: no architect. One licensed GC (General Contractor) executes the lean fit-out.
Phase 2: full A&E team (Architect + MEP + Structural + Acoustic + GC via preconstruction services).
Phase 1 GC selection
Phase 1 buildout is small ($40K, 6-10 weeks). We do not need a mid-market or national GC. We need one hungry, competent, RDU-based licensed GC who can:
- Deliver a small commercial fit-out in under 10 weeks
- Manage the certified rigger for pole installation
- Handle their own MEP (mechanical/electrical/plumbing) subs
- Provide a written scope + fixed bid before starting
- Meet Raleigh, Cary, or Durham code + inspection process (depending on final site) without drama
GC profile Phase 1
- RDU-based, NC-licensed
- Small commercial specialty (fit-outs $30K to $250K range)
- Experience with retail second-generation build-outs
- Existing subcontractor relationships in North Hills, Fenton, Waverly, Village District, or Brightleaf
- References from at least 2 completed fit-outs in the last 12 months
- Willing to work with a certified rigger (may not have done pole studio work before, but should be comfortable coordinating a specialty sub)
Where to find Phase 1 GC candidates
- Broker recommendations (once broker is retained per 02_BROKER_ROSTER)
- NC AGC (Associated General Contractors) member directory — Triangle chapter
- Referrals from other Cary / Raleigh small business owners
- Direct outreach to firms that have built out MEGA, JETSET Pilates, Club Pilates, or similar boutique studio spaces in the Triangle
Phase 1 GC interview questions
- Show me your last 3 small commercial fit-outs. Address, size, cost, timeline.
- Have you worked with a pole studio or aerial rigging installation? If not, are you comfortable coordinating a certified rigger sub?
- What is your process for a written scope + fixed bid?
- Who is my project manager? Are they on-site daily?
- How do you handle change orders? Ballpark change order percentage of contract value on your last 3 jobs.
- Local code + inspection process (Raleigh / Cary / Durham): any recent projects that hit inspection delays? What happened?
- What is your typical timeline from contract signing to permit + start of work?
Phase 1 GC selection criteria (100 points)
| Criterion | Weight |
|---|---|
| Small commercial fit-out track record (last 12 months) | 25 |
| Written scope + fixed bid clarity | 20 |
| Timeline commitment | 15 |
| Certified rigger coordination willingness | 15 |
| RDU code + inspection fluency (Raleigh / Cary / Durham) | 10 |
| Change order discipline | 10 |
| Triangle sub network depth | 5 |
Retain: top 1 above 80.
Phase 1 GC fee expectations
- Fixed bid on $40K buildout: GC’s fee is bundled inside. Typical GC margin on small commercial: 10 to 18 percent.
- No preconstruction services fee at this size.
- Deposit at contract signing: 10-20% (mobilization).
- Progress draws every 2 weeks against scope milestones.
- Final 10-15% withheld until punch complete.
Certified rigger for pole installation (Phase 1)
Separate specialty sub, not the GC. Non-negotiable — pole rigging is engineered work, not general handyman.
Rigger profile
- Certified by USITT (US Institute for Theatre Technology) or ETCP (Entertainment Technician Certification Program)
- Insurance minimum $2M general liability + $1M professional liability
- Written engineering letter certifying installation
Rigger sources
- Pole studio industry contacts (Pole Sport Organization can recommend)
- RDU-area theatrical rigging companies (they do concert/broadcast rigging at DPAC, Red Hat Amphitheater, PNC Arena — pole is analogous)
- Xpole or Lupit brand distributor (they may have preferred installers)
Rigger cost
- Included in the $6,000 “pole rigs installed” line item (see 03_BUILD_SPEC)
- Certified installation typically $600 to $1,200 per pole, so 6 poles at $900 = $5,400 for installation + $600 for poles themselves = ~$6,000
Structural engineer for Phase 1 pre-lease check
Also a specialty scope, not the GC.
What we need
- NC-licensed structural engineer walks the property BEFORE we sign an LOI
- Writes a letter confirming the ceiling can hold the pole rigging loads (1,500 lbs static per point, 10x dynamic factor)
- Certifies any additional ceiling reinforcement needed and provides a spec
Engineer options Phase 1
- Stewart (Raleigh HQ)
- SEPI Engineering (NC, Raleigh office)
- Lysaght & Associates (Raleigh)
- Any NC-licensed structural engineer with theatrical or industrial rigging experience
Engineer cost
- Site walk + written letter: $500 to $1,500 flat fee
- If reinforcement engineering is needed: additional $1,500 to $3,000 for spec + stamped drawings
- Included as part of GC scope or Bucket 1 legal/engineering line item
Phase 2 architect and GC selection (2028+)
Preserved from earlier planning for future reference. Full Phase 2 spec rewritten in 2028.
Phase 2 architect options
- Clark Nexsen (Raleigh HQ, hospitality + adaptive reuse practice)
- Little (Southeast, retail practice, Durham office)
- LS3P (Raleigh + Southeast, hospitality + adaptive reuse)
- Gensler Raleigh (national scale, hospitality/retail/lifestyle)
- Duda|Paine Architects (Durham, hospitality + mixed-use)
- Cline Design Associates (Raleigh, high-end residential + boutique commercial)
Interior design specialist partners to consider:
- Meyer Davis (NYC): premium hospitality + wellness
- Cass Calder Smith (SF, NYC): hospitality
- 22 Interiors (LA): boutique wellness
Pair a national design partner with an RDU-licensed AoR (Architect of Record — Clark Nexsen, LS3P, or Duda|Paine) to carry local permits.
Phase 2 GC options
- Holt Brothers Construction (Raleigh, hospitality + institutional)
- Clancy & Theys Construction (Raleigh HQ, institutional + hospitality, in NC since 1949)
- Barnhill Contracting (Raleigh, mid-market + institutional)
- Brasfield & Gorrie (Southeast regional with Raleigh office, strong healthcare MEP)
- Rodgers Builders (Southeast, hospitality track record)
- DPR Construction (national with Raleigh office, best-in-class MEP coordination)
Boutique alternatives:
- Riggs-Harrod Builders (Raleigh, mid-sized, interior strength)
- Frank L. Blum Construction (Winston-Salem / Raleigh, mid-sized, hospitality)
Phase 2 fee expectations
- Full A&E: 6-9% of construction cost = $200K to $400K on a $3.5M buildout
- MEP engineer: 1.5-2.5% of construction (may be bundled inside architect)
- Structural engineer: 0.75-1.5% of construction
- Acoustic consultant: $75K-$150K flat fee
- GC preconstruction: $15K-$30K flat
- GC fee: 4-6% of hard cost
- GC general conditions: 6-9% of hard cost
Complete Phase 2 selection process, timeline, RFP templates, and selection criteria will be rebuilt in 2028.
Related docs
- Property targets: 04_REAL_ESTATE_BUILDOUT/00
- Broker roster: 04_REAL_ESTATE_BUILDOUT/02
- Build spec: 04_REAL_ESTATE_BUILDOUT/03
- MEP + structural + acoustic (Phase 2): 04_REAL_ESTATE_BUILDOUT/05
- Buildout budget: 04_REAL_ESTATE_BUILDOUT/06